Region 8

Central City / Clear Creek

Central City/Clear Creek site location map
Site Type: Final NPL
City: Idaho Springs
County: Clear Creek
Street Address: Near town
ZIP Code: 80452
EPA ID: COD980717557
SSID: 0813
Site Aliases: Argo Tunnel, Five Mile Tunnel, Central City Mining District, Quartz Hill Tunnel, National Tunnel, Gregory Incline, Newhouse Tunnel
Congressional District: 2

What's New?

Updated September 2014

New RPM and CIC Named to Central City/Clear Creek Site Team

Les Sims, Remedial Project Manager, has over twenty years of experience working with Superfund-related cleanups. He has been with EPA for 12 years and currently works as Federal Remedial Project Manager (RPM) for Lowry Landfill, Eagle Mine and Central City/Clear Creek Superfund sites.

Jasmin Guerra, Community Involvement Coordinator, has been with EPA for four years and currently works as the Community Involvement Coordinator (CIC) for eight Superfund sites. Previously, she was an EPA Grants Specialist working closely with tribes, states and local governments.

Quartz Hill Project Nears Completion

The project to re-grade and cap Quartz Hill in Central City has been completed. Inert rock covering the site will prevent tailings from eroding into the storm sewer system or Clear Creek. All of the rock for the cap came from the stockpiles along the Central City Parkway, about a mile and a half from the site, reusing what otherwise would be considered waste material while reducing the size and improving the appearance of the remaining piles. Because the piles are comprised of native rock from the area, the completed project will resemble other rock cuts in the area. To accommodate rock placement, Quartz Hill was re-graded.

ESD Near Completion for Argo Tunnel Bulkhead Project

The Colorado Department of Public Health and Environment (CDPHE) and EPA will be issuing an Explanation of Significant Differences for the Argo Tunnel Discharge – Flow Control Bulkhead, part of the remedy for the Central City/Clear Creek Superfund site. The document explains differences between the 1991 selected remedy to address Argo Tunnel discharge and the modification to build a flow-through bulkhead in the tunnel during 2014.

The Argo Tunnel has a history of surge events that released acidic metals-laden mine water to the environment. The tunnel discharges acidic mine water containing dissolved metals that exceed both water quality and drinking water standards. Before the OU3 Record of Decision and the construction of the Argo Tunnel Water Treatment Facility, the Argo discharge flowed directly to the main stem of Clear Creek, killing or harming fish from the entry point to the city of Golden. The bulkhead will contain any surge events and reduce the potential for uncontrolled releases from the tunnel.

The bulkhead will not change the performance of the existing treatment technology or function of the Argo Tunnel Water Treatment Plant in Idaho Springs. The bulkhead will be able to control flow volume to the plant, resulting in reduced treatment costs.

Construction of the OU4 Water Treatment Plant Delayed

Due to the uncertainty of ongoing water use agreements negotiations with the town of Black Hawk and Gilpin County, construction of the OU4 Water Treatment Plant is on hold. EPA and CDPHE are working to implement a Superfund remedy for the North Fork of Clear Creek under the federal Comprehensive Environmental Response, Compensation and Liability Act.

The agencies amended the OU4 Record of Decision (ROD) in April 2010 calling for active treatment of metals-contaminated water impacting the North Fork of Clear Creek. The major components of the amended OU4 selected remedy include: the collection, conveyance and active treatment of the Gregory Incline discharge, Gregory Gulch ground water, and the National Tunnel discharge at a new water treatment plant. The sediment control remedy selected in the OU4 ROD did not change.

Shortly after the ROD amendment was signed, the town of Black Hawk and Gilpin County filed water rights claims in the North Fork of Clear Creek immediately below the outfall of the proposed water treatment plant. The filings triggered negotiations between Central City, Black Hawk, Gilpin County and the State of Colorado to develop an agreement to ensure minimum stream flows throughout the year. CDPHE and EPA are concerned that the water claims would reduce in-stream flows and prevent attainment of one of the Remedial Action Objectives (RAO) of the new water treatment plant, which is to create stream conditions protective of trout.

Five-Year Review of Cleanup Actions Launched

CDPHE and EPA are conducting a five-year review of cleanup actions performed under the Superfund program for the Central City/Clear Creek Superfund site. The review evaluates whether cleanup remedies are still protective of human health and the environment.

This is the fifth five-year review for the site, and is scheduled to be completed by the end of September 2014.

Church Placer Repository Undergoes Maintenance

Last fall CDPHE added cover soil, soil amendments, fertilizer and new seed to a seven-acre area of the Church Placer Repository cover where revegetation has performed poorly. The project was finished in November 2013, and revegetation is expected to take hold this spring. Plantings featured native vegetation tolerant of site conditions and beneficial for mine reclamation, including grasses, forbs, yarrow and other wildflowers. Mulch and straw wattles were installed to stabilize the site during the winter.

Top of Page


Site Description

The discovery of gold near Idaho Springs, Central City and Black Hawk in 1859 played a significant role in Colorado’s gold rush. For the next 20 years, the Black Hawk/Central City area was the leading mining center in Colorado primarily due to the construction of mills to process the gold and silver mined nearby. The silver crash in the 1890s brought a decline in mining to the area, but mining remained an important industry in Clear Creek and Gilpin Counties until about 1950. Only a limited number of mines are currently in operation.

Black Hawk Smelters and Gregory Lode
Black Hawk Smelters and Gregory Lode
(Denver Public Library Western History Images)

The Central City/Clear Creek Superfund Site consists of a 400-square mile watershed extending from the Continental Divide east to near Golden. The site is located in Gilpin and Clear Creek Counties. Popular for activities like fishing, rafting, kayaking, and gold panning, it also serves as a drinking water source for over 500,000 people in the Northwest Denver Metro area.

In September of 1983, the Central City/Clear Creek site was placed on the National Priorities List (NPL), or Superfund list. Historic gold mining and mine wastes left behind in the Clear Creek basin contaminated the watershed. Elevated levels of metals in Clear Creek were the driving factors in the listing of the site. Only a small fraction of this watershed is actually impacted by the historical mining operations making cleanup more difficult. Because mine wastes are scattered throughout the watershed, cleanup goals focus on improving water quality rather than individual tasks.

Map of the Superfund site and surrounding area, January 2013

Top of Page


Site Risk

Media Affected Contaminants Source of Contamination
soil, surface water, leachate, groundwater, liquid waste heavy metals like zinc, copper, manganese, cadmium, lead and arsenic mining and milling operations within a watershed

EPA and the Colorado Department of Public Health and the Environment (CDPHE) assessed potential impacts to human health and the environment from mine waste piles and tunnel discharges.

The environmental issues addressed by these projects include metals contamination in the waters of Clear Creek, particularly the North Fork, and management of mine tailings, waste rock and tunnel drainage to prevent further contamination of the Creek.

Contaminants of concern (COCs) for aquatic life include zinc, copper, cadmium and manganese. These metals are found in surface water and primarily affect trout, aquatic insects and other aquatic organisms.

The COCs for humans are arsenic and lead. Health risks could result from long-term drinking of groundwater containing high concentrations of these metals, the incidental ingestion of tailings and waste rock, and inhalation of airborne dust.

Top of Page


Remedial Action Objectives

Surface Water

  • Reduce in-stream metals concentrations and sediment transport to minimize the impacts on water quality and habitat, and to maximize reasonably attainable water uses of the North Fork of Clear Creek. These actions also will support the survival of a reproducing brown trout population in the North Fork of Clear Creek.
  • Reduce in-stream metals concentrations and sediment transport in North Clear Creek with the purpose of reducing adverse water quality and habitat impacts on the main stem of Clear Creek, to protect aquatic life and to support a viable reproducing brown trout population in the main stem of Clear Creek.
  • Ensure that in-stream metals concentrations do not degrade drinking water supplies diverted from the main stem of Clear Creek.
  • Reduce the toxicity to benthic aquatic organisms living at the surface water/sediment interface or in sediment to levels that are protective of aquatic life.

Tailings/Waste Rock

  • Control and/or reduce run-on and runoff from tailings/waste rock piles to minimize generation of contaminated runoff and/or ground water, and to reduce sediment loading of streams.
  • Reduce exposure to arsenic and lead from incidental ingestion of surface tailings/waste rock and other mine wastes to minimize the potential threat to human health.

Groundwater

  • Control and/or reduce metals loading from groundwater to reduce in-stream metals concentrations.
  • Ensure that contaminated ground water does not adversely impact human health.

Air

  • Control airborne metals contaminants in residential areas.

Top of Page


Cleanup Progress

2013

  • Work began on designs for the North Fork Clear Creek water treatment facility.
  • EPA and CDPHE started work on the Gold Hill tailings pile in Central City. This work entailed re-grading and partial removal of some of the tailings. After this work was completed a cap was placed over the pile.
  • Initial work began on an explanation of significant differences that called for the installation of a flow control system inside the Argo Tunnel bulkhead to help control mine water draining from the adit.
  • The Colorado Department of Transportation (CDOT) completed work on State Highway 119 in June. The project included removal of mining waste in North Clear Creek, construction of the building site for the new OU4 water treatment plant and a shared-use path along the North Fork of Clear Creek, and stream stabilization and wetlands construction.

2012

  • Designs for a new active water treatment plant were undertaken at Operable Unit 4 (OU4). This plant will be designed to treat mine waste water emanating from the Gregory Incline, National Tunnel, and Gregory Gulch. Construction date for this project is anticipated to begin in 2014.
  • Work was completed on remediation of the mine waste rock piles located in OU4.

2009

  • Logo of the American Recovery and Reinvestment Act of 2009
    The Central City/Clear Creek Superfund site received $2.16 million from the American Recovery and Reinvestment Act of 2009 to complete the sediment reduction component and pipeline conveyance of OU4 Remedial Action work.
  • Work began in July of 2009 on the sediment reduction and mine waste pile remediation component of OU4 Phase III. This work focused on the mine waste piles impacting the North Fork of Clear Creek. Projects included:
    • relocating and consolidating various waste rock piles at the Church Placer Repository
    • erosion-control measures at other mine waste piles
    • Some waste rock piles were left in place, slopes were re-graded and run-on control ditches or other erosion controls were constructed.
  • CDPHE, EPA, and CDOT worked jointly on a highway curve straightening project on the North Fork of Clear Creek near Black Hawk. This project used the rock generated from the curve straightening project for the rock cover at the Church Placer Repository and the Pittsburgh waste pile. This project led to stream sediment improvements and habitat restoration.
  • The city of Black Hawk consolidated two mine waste piles and used the Church Placer Repository for the mine wastes.

2008

Church Placer property
Church Placer property before work began
  • Purchase of the Church Placer property was a major milestone for completing Phase II work for Operable Unit 4 (OU4). Once the new access road was completed crews worked hard preparing the property with erosion control measures necessary before other mine wastes could be accepted.
  • Sediment detention basins, rock check dams, rock drop structures, and run-on control ditches were built to help with sediment control and slow down the flow of water. Some eroded tailings were removed from the channel and placed on a more stable site with existing mine waste piles. Other mine waste piles were re-graded and a rock cover placed over them. This work occurred primarily in Russell and Nevada Gulches and included at least six waste rock and tailings piles.

2007

  • Phase I of Operable Unit 4 work included the construction of two sediment detention basins and erosion control measures at five mine waste rock and tailings piles. Erosion control measures included run-on and run-off ditches, re-grading of steep or eroding slopes, and placing rock at the bottom of the pile if necessary. This work was completed in Russell Gulch, Nevada Gulch, South Willis Gulch and Gregory Gulch.
  • CDPHE and EPA formed partnerships to complete two separate projects:
    • Working with the Colorado School of Mines, a pilot project testing various passive systems known as "sulfate-reducing bioreactors" was used to treat water from the National Tunnel.
    • Black Hawk/Central City Sanitation District along with CDPHE and EPA constructed a wetlands project to filter and remove metals from North Clear Creek water.

2006

  • The Record of Decision for Operable Units 3 and 4 was amended to add an on-site mine waste repository.
  • In an effort to address significant sources of metals contamination to the main stem of Clear Creek, structures to pipe water from both Virginia Canyon and the Big 5 Tunnel to the Argo Water Treatment Facility were built.

2005

Argo water treatment plant
Argo water treatment plant
  • The Argo Water Treatment Facility began using hydrated lime in its treatment process of metals-laden water from the Argo Tunnel.
  • Design work for the reclamation of the Golden Gilpin Mill was completed.
  • Construction of the cap for the Chase Gulch #2 mine waste pile was completed.
  • CDPHE, CDOT, EPA and the city of Idaho Springs worked collaboratively to design and construct a conveyance system to take the water from the Big 5 Tunnel drainage and pond to the Argo Water Treatment Facility. As part of this project the Big 5 Pond has been drained, filled and capped.
  • A cutoff wall and sediment basins were constructed along with general storm water management maintenance the county needed in Virginia Canyon to assist with the collection of the metals-laden surface and ground water.
  • The Record of Decision for Operable Unit 4 (OU4) was signed September 29, 2004 for the cleanup of North Fork of Clear Creek and its tributaries as well as Quartz Hill, Gregory Incline, and National Tunnel mine discharges.

2004

  • The five-year review and update of the Community Involvement Plan were completed.
  • A public meeting was held to discuss the proposed cleanup plan and preferred alternative for OU4. Comments were accepted from the public about the cleanup alternatives and the OU4 Record of Decision was finalized in September.
  • Work was completed in Virginia Canyon, which included removing mine waste piles from the Two Brothers Mine, the Little #6, and collecting groundwater to divert to the Argo water treatment plant.
  • The Clear Creek Watershed Foundation completed cleanup of waste piles at the Leavenworth, Sydney and Dibbens mines.

2003–2000

  • In 2003, an amendment was completed to the ROD for OU3 to change the remedial action at the Burleigh Tunnel to a no-action response.
  • In 2000, CDPHE and EPA began looking at locations for use as an on-site mine waste repository. Three locations were considered: the Gem/Franklin in Clear Creek County, the Glory Hole and the Druid/Church Placer, both located in Gilpin County.

Pre-2000

  • In 1999, CDPHE began high-flow and low-flow surface water monitoring on Clear Creek below the Burleigh Tunnel.
  • During 1998, one of the wetland components at Operable Unit 3 (OU3) was decommissioned and the other component operated until 1999.
  • April 1998, the Argo Water Treatment Plant was completed and began operation, removing about 99 percent of the metals from the mine water.
  • August 1993, pursuant to the OU3 Record of Decision, a passive treatment wetland was constructed as a pilot-scale demonstration project at the portal of the Burleigh Tunnel.
  • Cleanups of numerous tailings and waste rock piles occurred during the 1990s.
  • The OU3 Record of Decision was signed September 30, 1991.

Top of Page


Community Involvement

Community involvement plays an important role in the Superfund process. EPA uses a number of different tools and resources to promote effective, on-going, meaningful community involvement. The goals of the Superfund community involvement program are to:

  • Keep communities affected by sites informed throughout the cleanup process
  • Provide opportunities for communities to comment and offer their input about site cleanup plans
  • Facilitate the resolution of community issues tied to a site

Team members regularly meet with local elected officials, groups like the Upper Clear Creek Watershed Association, Black Hawk Rotary Club and individuals as needed. It is important to reach out to communities to understand any concerns the community may have as work progresses.

CDPHE and EPA have provided the community with information about the work being done by using fact sheets, public notices and press releases in local papers, a community involvement plan, maintaining an information repository, public meetings, individual or small group informal meetings, and occasional emails.

Community interviews will be conducted during the five-year review that is underway. In addition, interested community members may provide comments to the site team listed in Contacts.

Top of Page


Reuse

EPA places a high priority on land reuse as part of its Superfund response program mission. The agency tries to select cleanup options that encourage and support future use of a site. We use two fundamental methods to facilitate reuse of Superfund sites:

  • Exploring future uses before the cleanup remedy is implemented, an approach that gives the Agency the best chance of designing cleanup remedies to support the likely future use of a site
  • Working with landowners and communities to remove barriers not considered necessary for the protection of human health or the environment at those sites where remedies are already in place

One option for reuse is the siting of clean and renewable energy projects on contaminated (or formerly contaminated) lands. As part of this effort, EPA is evaluating the potential for energy projects on these properties and working with landowners and communities to identify ways to remove barriers to such projects.

In 1992, limited stakes gaming began in Central City and Black Hawk. As property for the casinos was developed, many mine waste cleanup projects were implemented. For example, mine wastes were capped or covered when a parking lot was constructed.

Top of Page


Land Use Controls and Other Institutional Controls

Land use controls are the most common type of institutional control (IC). ICs are administrative or legal controls that help reduce the likelihood for human exposure to contamination. ICs can also help protect the integrity of the remedy. Examples of ICs are:

  • Zoning ordinances
  • Environmental covenants
  • Deed notices
  • Well-drilling restrictions
  • Building permits
  • Informational advisories

Remediated areas where mine waste is left in place are subject to environmental covenants between CDPHE and the landowner. A number of settlements or agreements were entered into with casino developers to assure that development of gaming properties is consistent with mine waste remaining on-site.

Top of Page


Five-Year Reviews

EPA or the lead agency conducts five-year reviews following the start of a Superfund cleanup when contamination is left on the site. These reviews are repeated every five years. We use these reviews to determine:

  • How the remedy is working
  • If the remedy remains protective of human health and the environment

This is the fifth five-year review for the site, and is scheduled to be completed by the end of September 2014.

Top of Page


Site Documents

You will need Adobe Reader to view some of the files on this page. See EPA’s About PDF page to learn more.

Update Fact Sheet (PDF), August 2014(6 pp, 1.1 MB)

Update Fact Sheet (PDF), October 2012(4 pp, 155 K)

Update Fact Sheet (PDF), November 2011(7 pp, 237 K)

Update Fact Sheet (PDF), August 2010(6 pp, 364 K)

Update Fact Sheet, July 2009

Update Fact Sheet, September 2008

Records of Decision (RODs)

Amendments to Records of Decision (RODs)

Five-Year Reviews

Top of Page


Contacts

EPA

Les Sims
Remedial Project Manager
U.S Environmental Protection Agency, Region 8
1595 Wynkoop Street (8EPR-SR)
Denver, CO 80202-1129
303-312-6224
800-227-8917 ext. 312-6224 (toll free Region 8 only)
sims.leslie@epa.gov

Jasmin Guerra
Community Involvement Coordinator
U.S. Environmental Protection Agency
1595 Wynkoop Street (8OC)
Denver, CO 80202-1129
303-312-6508
800-227-8917, ext. 312-6508 (toll free Region 8 only)
guerra.jasmin@epa.gov

Site Information Repositories:

Gilpin County Courthouse
203 Eureka Street
Central City, CO 80427
303-582-5451

Clear Creek Watershed Foundation
2060 Miner Street
Idaho Springs, CO 80452
303-567-2699
Please call for an appointment

Colorado Department of Public Health and Environment
HMWMD Records Center
4300 Cherry Creek Drive South
Denver, Colorado 80246-1530
303-692-3331
888-569-1831 ext. 3331 (toll free)
303-759-5355 FAX
comments.hmwmd@state.co.us
By appointment only

EPA Superfund Records Center
1595 Wynkoop Street
Denver, CO 80202-1129
To request copies of administrative record documents call:
303-312-7273
800-227-8917 ext. 312-7273 (toll free Region 8 only)

CDPHE

Mary Boardman
State Project Manager
Colorado Department of Public Health and Environment
Hazardous Materials and Waste Management Division
4300 Cherry Creek Drive South B2
Denver, CO 80246-1530
303-692-3413
FAX 303-759-5355
mary.boardman@state.co.us

Warren Smith
Community Involvement Manager
Colorado Department of Public Health and Environment
Hazardous Materials and Waste Management Division
4300 Cherry Creek Drive South B2
Denver, CO 80246-1530
303-692-3373
FAX 303-759-5355
warren.smith@state.co.us

Top of Page


Photo/Video Gallery

Click on a thumbnail below to view the full size image.

Gregory Gulch, 1865(Denver Public Library Western History Images)
Water flolwing in Gregory Gulch
Water flowing in Gregory Gulch
Church Placer Mine Waste Repository 2008
Dump truck at Church Placer Mine Waste Repository 2009
North Fork Clear Creek
Hampden Mine Waste Pile
Hampden Mine Waste Pile Phase I
Hampden Mine Waste Pile Phase II
Chase Gulch Mine Waste Pile 2006
Chase Gulch Mine Waste Pile 2007

Top of Page


Links

The following links exit the site Exit

Central City/Clear Creek site at the Colorado Department of Public Health and Environment

Clear Creek Watershed Foundation

Top of Page